Taking to the Heights: Installing a 10m Process Tank
A recent project for CLT Group saw one of our team leaders, Chris, taking to the Bosun’s chair to get the job done.
We were tasked with installing a 10-metre-tall process tank, weighing 7 tonnes, which was top & tailed into position between Mary, our JMG electric crane, and the onsite crane. Due to the tank’s restricted location, Chris utilised the Bosun’s chair to safely remove the slings once the lift was complete.
All in a day’s work for our highly trained and versatile team, delivering safe, efficient solutions in even the most challenging environments.