Part Two: Final Compressor Installation Complete

Following the successful removal and replacement of the original compressor system, the team recently returned to our valued soft drinks manufacturing client to install the third and final compressor unit — bringing this project to a close.

Weighing in at 7.3 tonnes, this final unit required a precise and carefully coordinated approach:

  • Offloaded using Mary, our electric JMG MC160 crane, with a lifting beam

  • Supported in the entranceway using blocks to safely bridge a sizeable drop

  • Moved into position using skates and the Hyster S7

All completed with minimal disruption to the client’s operations — thanks to the experience, planning, and teamwork of everyone involved.

It’s always rewarding to deliver a project from start to finish with safety, efficiency, and professionalism at the core.

Recent Posts

Jane’s First Lift: Our New Electric Crane Makes Debut

9 January 2026

Dirty Work, Done Right: Conveyor System Safely Removed at Evergreen Garden Care

5 January 2026

A Huge Thank You to All Our Customers

29 December 2025

Supporting a Smooth Installation at a New Packaging Facility

23 December 2025

View All

Get Your Free Quote

Simply fill in your details, and a member of our team will get back to you promptly with a free, no-obligation quote tailored to your needs.

Contact Us

  • TEP Machinery Movement Limited
  • Unit 8 Swinnow View,
  • Leeds,
  • LS13 4TZ

    Download Our

    Free Brochure

    For more details on how we handle your data, please view our Privacy Policy.

    TEP Machinery