30th July 2025
Part Two: Final Compressor Installation Complete
Following the successful removal and replacement of the original compressor system, the team recently returned to our valued soft drinks manufacturing client to install the third and final compressor unit — bringing this project to a close.
Weighing in at 7.3 tonnes, this final unit required a precise and carefully coordinated approach:
-
Offloaded using Mary, our electric JMG MC160 crane, with a lifting beam
-
Supported in the entranceway using blocks to safely bridge a sizeable drop
-
Moved into position using skates and the Hyster S7
All completed with minimal disruption to the client’s operations — thanks to the experience, planning, and teamwork of everyone involved.
It’s always rewarding to deliver a project from start to finish with safety, efficiency, and professionalism at the core.